Sunday, April 25, 2010

RGGVY review by MIC Power

A review meeting was held at circuit house today in presence of MIC Power GoWB and Sabhadhipati. Zonal Manager WBSEDCL, Project Manager of RGGVY and Agencies attended the meeting. DM and Sabhadhipati, Karmadhyakshya, ADM Genral also attended.
Salient decisions are :-
  • Supply of Poles to be completed by August 2010 @ 14000 to 15000 per month for all three packages in Burdwan district.
  • Supply of single phase meters for service connection is to be completed by October 2010 at the rate of 35000 to 40000 per month.
  • All works related to erection of poles, wire, service connections and energisation to be completed by December 2010. Block level monitoring mechanism to be further strengthened and regular meetings to be held in detail so that the target work is completed in time.
  • Service connection charges for APL families may be reduced from present Rs 3000 per connection to Rs 500 per connection. WBSEDCL has agreed to bear the extra expenses. WBSEDCL with the help of GPs must do the survey and furnish location wise requirement of APL connections, uncovered families by the Middle of may 2010. Necessary circular is being issued. Details will be discussed in Sub divisional level meetings starting from 29th April 2010.
  • Approved drawings of each location must be shared with local GP so that they may assist the WBSEDCL authorities in identifying uncovered families and APL. Basically, APL and uncovered families are required to be told to apply for service connection through camp mode at the GP level.
  • SDOs are required to update us on monitoring mechanism in blocks as per the circular issued in the beginning of this month.